VolumePre-market / after-hoursUnusual moveNotable move · hover or tap for why
Forward P/E-6.63
Market Cap$594.86M
Open$6.64
Trailing P/E-2.17
Day Range$6.41–$7.47
Dividend Yield0.00%
52W Range$5.97–$37.88
EPS-$3.75
Volume5.73M
Avg Volume6.38M
50-Day Avg$13.30
200-Day Avg$15.01
Why is FCEL moving?
FCEL rose about 5% in heavy volume as the stock rebounded from an intraday dip to around $6.40, likely helped by renewed speculative interest in fuel cell and clean-power stocks, including news that Tradr would launch new leveraged ETFs, despite the overhang of securities class action lawsuit notices.
Wall Street's consensus on FCEL is a Buy, with 5 of 9 analysts (55.6%) bullish, 3 (33.3%) neutral and just 1 (11.1%) bearish. The average price target is $21.78 (median $20.00), within a wide range of $8.00 (bearish Wells Fargo, Underweight) to $32.00 (B. Riley Securities, Buy). That spread shows real disagreement on how much value the data center power story deserves. Sentiment improved sharply this summer, led by upgrades to Buy from Jefferies (PT $24), Canaccord Genuity (PT $30), B. Riley (PT $32) and UBS (PT $27). Targets rose far above their earlier single-digit and low-teens levels. Coverage has also widened since mid-September. Oppenheimer started at Outperform (PT $24), while Barclays (Equal-Weight, $20) and Citigroup (Neutral, $19) took more cautious stances. Jefferies trimmed its target to $20 from $24 on Sept. 8 but kept its Buy rating, a sign that enthusiasm is becoming more measured. Recent news shows the stock is volatile. It jumped about 18% on Nov. 23 on AI-related enthusiasm, but it has had sharp drops since September, and shareholder law firms have announced class action investigations and lawsuits. Even so, the mid-teens to mid-$20s targets from most firms point to continued upside potential, tempered by execution and legal risk.
▲ Bull caseA pipeline of roughly 10 gigawatts, 97% data center related, plus a $3.6 billion committed and awarded backlog supports growth. The Fit Energy agreement, Siemens collaboration and a 75 MW Texas reservation signal visible demand, prompting target increases toward $30-$32 and a shift from a show-me story.[10][1][2]
▼ Bear caseProposals have limited visibility of converting into profitable contracts. The Texas reservation still lacks a definitive agreement, and Fit Energy may not proceed with later phases. Competitive pressure in data center opportunities and weak traction against rivals led some analysts to trim targets to $6 and rate shares Underweight.[2][3][1]
▲ Bull caseManagement targets positive adjusted EBITDA in fiscal Q4 2027, while expanding production toward a 100 MW annualized rate. Analysts expect losses to narrow, with EPS estimates improving from -$2.09 to -$0.96, and see revenue growing about 42% annually, supporting higher future multiples and margins.[9][5][1]
▼ Bear caseGross losses widened after a $17 million Fit Energy pricing charge, and Q3 revenue fell 29% while missing estimates. Manufacturing cost concerns persist, and forecasts show no profitability for three years. One Sell-rated analyst sees no viable path to profitability and possible fund exhaustion in FY2027.[6][9][1]
▲ Bull caseUnrestricted cash of $658.1 million, no corporate convertible or high-yield debt, and a fully funded Torrington buildout give FuelCell runway to scale. EXIM-backed project financing adds support, and the stock trades at a discount to peers such as Bloom Energy, supporting consensus targets near $21.80.[3][2][5]
▼ Bear caseShares outstanding rose from 46 million to 80 million since October 2025, and operating losses keep draining cash. Fit Energy warrants cover up to 12 million shares at $26.44, while securities class actions and a CFO transition add risk. AAII rates valuation Expensive, with negative free cash flow tempering upside.[10][3][9][8]
FuelCell Energy was swept up in a violent AI-power selloff that hit fuel-cell peers like Bloom Energy and Plug Power, as hot PCE inflation, new Section 301 tariff proposals and renewed AI doubts pushed the Nasdaq sharply lower. FCEL fell as low as $6.41 (near its $5.97 52-week low) but staged a late-session rebound to close up 4.79% at $7.44 and edged slightly higher after hours, recouping part of Tuesday's 8.7% drop. Backdrop remains cautious: shares are down roughly 38% in a month, Q3 revenue fell 29% with a $17M Fit Energy-related charge, law firms are investigating, and the next catalyst is Q4 earnings, though analysts' average target (~$21) sits far above the price.
FuelCell Energy shares jumped as the AI data-center power trade rebounded after Nvidia's board reinstated CEO Jensen Huang, which fueled a broad relief rally (Nasdaq +6.5%, S&P 500 +4.7%) following last week's tech-led correction. Fuel cell peer Bloom Energy rallied about 18% and Plug Power also gained. Data centers made up roughly 97% of FuelCell's pipeline, and the stock ended up 16.29% at $7.78 (about +1.5% after hours), snapping a seven-day losing streak. The stock is still down about 69% over six months and far below the $21.80 consensus target. Separately, the company filed an 8-K approving its fiscal 2027 executive long-term incentive plan, and recently completed a $49M EXIM-backed financing for a South Korea project. Investors are watching the next quarterly report for Fit Energy delivery progress.
FuelCell Energy shares slumped as the AI-infrastructure trade unwound, with the Nasdaq down 2.49% and the S&P 500 down 1.92% ahead of Nvidia earnings and the Anthropic IPO. Data-center power peers also fell: Bloom Energy and Ballard dropped sharply, and Plug Power slid. The stock closed down 9.61% at $8.75, on below-average volume, and was roughly flat after hours. It is down about 38% over the past month. Investors are weighing the company's AI data-center pitch, including the StabilityMax testbed announced Nov. 10, against Q3 gross losses, a $17M CEPA charge, a pending securities class action, and a consensus 'Hold' rating with a ~$21.80 target. A director's September insider purchase at about $15.05 is now well underwater. A technical read flags a persistent downtrend.
FuelCell Energy shares slumped as a second day of AI-infrastructure selling, tied to turmoil around Nvidia's leadership and rising Treasury yields (10-year near 5.17%), hit high-beta power-for-data-center names. The stock closed down 5.56% at $9.68, roughly 38% lower over the past month. Bloom Energy fell about 5% and Plug Power about 10%, while the Industrials sector ETF was comparatively steadier. Company-specific news was mildly supportive: it joined the DOE-led StabilityMax project to build a fuel cell testbed for AI data centers. Overhangs remain, including a fiscal Q3 gross loss with a $17M charge on the Fit Energy contract, a securities class action, and short interest of about 31% of float. The analyst median target of about $21 sits well above the current price. Shares were little changed after hours.
$10.28 ↘ 4.99% at Close·$10.40 ↗ 1.17% After Hours
FuelCell Energy announced its participation in StabilityMax, a three-year DOE-led project with national labs to build a 1.25 MW AI data center power testbed in Connecticut. The news did not prevent a pullback, and shares closed down about 5% as hotter-than-expected October CPI and Fed rate-hike talk (Waller floated a 50bp move) pushed Treasury yields higher and weighed on rate-sensitive clean energy peers like Fluence and Sunrun. Investors are also weighing the securities class action tied to the Fit Energy agreement and the $17M charge, with the lead-plaintiff deadline falling on Nov. 10. Texas data center policy risk to its planned 75 MW project also remains a concern after Monday's 8.7% rebound. Shares were up about 1% after hours.
$10.82 ↗ 8.63% at Close·$10.86 ↗ 0.37% After Hours
FuelCell Energy shares surged in a broad rebound for fuel cell and AI-power names, as a sharp oil decline and a tech-led rally lifted the S&P 500 about 2.3% and industrials roughly 4% after last week's post-election selloff. Bloom Energy gained on a 900 MW NTT DATA deal, reviving on-site data center power sentiment, though FuelCell remains exposed to Texas data center policy risk tied to its planned 75 MW project. Overhangs include a securities class action over the Fit Energy agreement, with a November 10 lead plaintiff deadline, and the $17 million Phase 0 charge from the September quarter. The stock closed up 8.63% at $10.82, edging slightly higher after hours, well below the $14.40 level after the September earnings drop. Consensus analyst target is about $21.80.
FuelCell Energy shares closed sharply higher, rebounding from the prior session's post-election rout as fuel cell peers also bounced; Plug Power and Bloom Energy rose.
FuelCell Energy shares slumped in a broad AI and data-center rout that followed Democratic midterm wins, as investors feared tighter data center regulation, including a moratorium promised by Texas's…
$10.54 ↘ 5.98% at Close·$10.51 ↘ 0.28% After Hours
FuelCell Energy shares slumped as a Democratic sweep of Congress triggered a sharp selloff in AI and data-center infrastructure names, a group FuelCell has increasingly targeted, with its sales focus…
$11.21 ↗ 6.76% at Close·$11.20 ↘ 0.09% After Hours
FuelCell Energy shares rebounded sharply, rallying alongside fuel cell and power-equipment peers after Bloom Energy jumped on a Barclays upgrade and a California Resources MOU, though FuelCell was…
$11.22 ↘ 7.88% at Close·$11.22 ↗ 0.00% After Hours
FuelCell Energy shares tumbled in a broad risk-off session for AI-linked and data-center power names, even after the company completed the second tranche of its $49 million EXIM-backed financing for…
$12.18 ↘ 1.62% at Close·$11.61 ↘ 4.68% After Hours
FuelCell Energy announced completion of the second ~$24.7 million tranche of its $49 million EXIM-backed financing for five 2.8-MW Blocks bound for Gyeonggi Green Energy in South Korea.
$12.38 ↗ 1.64% at Close·$12.13 ↘ 2.04% After Hours
FuelCell Energy appointed digital-infrastructure executive Peter Hopper, who co-led the $11B Switch take-private, to an expanded ten-member board as it pushes its data center power strategy.
$12.18 ↗ 6.28% at Close·$12.32 ↗ 1.15% After Hours
FuelCell Energy shares rallied as fuel cell peers extended a rebound from post-earnings selling, with Bloom Energy up about 6% and Plug Power about 3%, following Bloom's strong Q3 beat and the…
FCEL gained 18.8% to close at $17.76. Intraday range of $2.96 ($15.12 – $18.08) spanned 19.6% in a volatile session. Volume reached 13.93M shares (1.7× the 20-day average). Closed near the session high, with buyers in control into the close.
+18.8%
Jul 30, 2026
Big RallyGap Up 8.3%
FCEL gained 30.6% to close at $23.62, opening 8.3% above the prior close. Intraday range of $4.18 ($19.58 – $23.76) spanned 21.3% in a volatile session. Closed near the session high, with buyers in control into the close.
+30.6%
Jun 30, 2026
Big RallyNew 52-Week HighGap Down 3.0%
FCEL gained 20.8% to close at $36.01, opening 3.0% below the prior close. Intraday range of $8.99 ($28.89 – $37.88) spanned 31.1% in a volatile session. Volume reached 26.75M shares (2.1× the 20-day average). Set a new 52-week high of $37.88.
+20.8%
Jun 29, 2026
Big RallyNew 52-Week HighGap Up 6.4%
FCEL gained 24.2% to close at $29.80, opening 6.4% above the prior close. Intraday range of $5.55 ($25.25 – $30.80) spanned 22.0% in a volatile session. Volume reached 21.21M shares (1.7× the 20-day average). Set a new 52-week high of $30.80. Closed near the session high, with buyers in control into the close.
+24.2%
Jun 26, 2026
Big RallyGap Up 2.6%
FCEL gained 22.1% to close at $24.00, opening 2.6% above the prior close. Intraday range of $6.17 ($19.33 – $25.50) spanned 31.9% in a volatile session. Volume reached 27.12M shares (2.4× the 20-day average).
+22.1%
Jun 18, 2026
Big RallyGap Up 3.2%
FCEL gained 20.0% to close at $24.04, opening 3.2% above the prior close. Intraday range of $5.03 ($19.33 – $24.36) spanned 26.0% in a volatile session. Closed near the session high, with buyers in control into the close.
+20.0%
Jun 5, 2026
Sharp DropGap Down 4.7%
FCEL fell 19.0% to close at $17.33, opening 4.7% below the prior close. Intraday range of $3.30 ($17.20 – $20.50) spanned 19.2% in a volatile session. Closed near the day's low as sellers pressed into the close.
-19.0%
May 21, 2026
Big RallyNew 52-Week High
FCEL gained 30.5% to close at $26.38. Intraday range of $7.16 ($19.74 – $26.90) spanned 36.3% in a volatile session. Volume reached 22.36M shares (2.0× the 20-day average). Set a new 52-week high of $26.90. Closed near the session high, with buyers in control into the close.
+30.5%
Apr 29, 2026
Big RallyNew 52-Week HighVolume 4.3× avgGap Up 14.7%
FCEL gained 37.2% to close at $13.64, opening 14.7% above the prior close. Intraday range of $2.67 ($10.99 – $13.66) spanned 24.3% in a volatile session. Volume reached 18.66M shares (4.3× the 20-day average). Set a new 52-week high of $13.66. Closed near the session high, with buyers in control into the close.
+37.2%
Apr 22, 2026
Big RallyNew 52-Week HighVolume 6.6× avgGap Up 5.3%
FCEL gained 24.3% to close at $11.80, opening 5.3% above the prior close. Intraday range of $1.89 ($9.99 – $11.88) spanned 18.9% in a volatile session. Volume reached 17.06M shares (6.6× the 20-day average). Set a new 52-week high of $11.88. Closed near the session high, with buyers in control into the close.
+24.3%
Apr 20, 2026
Big RallyVolume 4.4× avg
FCEL gained 19.3% to close at $8.65. Intraday range of $1.64 ($7.06 – $8.70) spanned 23.2% in a volatile session. Volume reached 6.46M shares (4.4× the 20-day average). Closed near the session high, with buyers in control into the close.
+19.3%
Dec 18, 2025
Big RallyVolume 6.9× avgGap Up 17.6%
FCEL gained 22.0% to close at $9.64, opening 17.6% above the prior close. Intraday range of $1.65 ($9.25 – $10.90) spanned 17.8% in a volatile session. Volume reached 12.94M shares (6.9× the 20-day average).
The report weighs FCEL’s data-center opportunity and substantial cash against below-cost initial product economics, production shortfalls, dilution, and uncertainty over whether options and reservations become firm orders. Its central question is whether manufacturing scale can lower unit costs before cash is consumed; the publisher says the research uses AI with human editorial review.
The thesis depends on data-center reservations converting into funded orders and higher factory utilization lowering costs below contract pricing. It also highlights service-performance, cash-burn, dilution, and carbon-capture commercialization risks; its evidence assessment is mixed, with strengthening, unclear, and weakening propositions.
The author argues that FCEL’s production limits, persistently negative margins, share dilution, and weak backlog conversion undermine the value of its technology and data-center opportunity. The report concludes with a sell view, citing operating and financing risks and comparing FCEL unfavorably with scaled competitors.
The initiation report rates FCEL Sector Underperform, arguing that its evolving business model, uncertain market share and commercialization prospects, and low confidence in estimates create significant operating and valuation risk. Its DCF analysis supports a $3 price target; the report is dated and reflects its 2021 assumptions.
This historical initiation report recommends buying FCEL, arguing that its molten-carbonate fuel-cell technology, expected commercialization, distribution alliances, and potential cost reductions could position it for growth in distributed power. It supports the thesis with technology and manufacturing analysis and a valuation using DCF, discounted earnings, and price-to-revenue; its forecasts and target are from 2001.
Q3 FY2026 revenue was $33 million, down 29% YoY from $46.7 million, driven by fewer South Korea module deliveries, lower generation output (Groton outage), and lower advanced technology contract revenue.
Gross loss of $24.5 million (vs $5.1 million loss prior year), driven by $17 million in charges related to inventory write-downs and firm purchase commitment losses tied to Phase Zero of the FuelCell/Fit Energy agreement, as production ran at ~37MW annualized vs. the 100MW target.
Total committed and awarded capacity backlog reached $3.6 billion as of July 31, 2026 ($1.3 billion committed, up 4.1% YoY; $2.4 billion newly disclosed "awarded capacity backlog" category, largely tied to the Fit Energy CPA covering up to 380MW across four phases and a subsequent 75MW Texas data center capacity reservation agreement).
Company ended the quarter with $737.3 million in total cash (up from $440.9 million), no corporate convertible or high-yield debt, and reaffirmed the Torrington, CT manufacturing expansion to 500MW annualized capacity by June 2028 is fully funded (estimated $200-275 million total cost), with a near-term goal of reaching 100MW annualized production rate by October 2026.
Company now targets positive adjusted EBITDA in Q4 fiscal 2027, contingent on scaling production to at least 100MW, converting awarded capacity backlog (including Fit Energy phases and the ~10 gigawatt sales pipeline) into committed contracts, and continued manufacturing cost reduction as volume increases.
Thank you for standing by. My name is Jalen, I will be your conference operator today. At this time, I would like to welcome everyone to the FuelCell Energy third quarter of fiscal year 2026 financial results conference call. All lines have been placed on mute to prevent any background noise. After the speaker's remarks, there will be a question-and-answer session. If you would like to ask a question during this time, simply press star followed by the number one on your telephone keypad. If you would like to withdraw your question, simply press star one again. I would now like to turn the conference over to Michael Bishop, Chief Financial Officer. You may begin.
Michael Bishop
Thank you, operator. Good morning, everyone, and thank you for joining us on the call today. This morning, FuelCell Energy released our financial results for the third quarter of fiscal year 2026, and our earnings press release is available in the Investors section of our website at www.fuelcellenergy.com. In addition to this call and our earnings press release, we have posted a slide presentation on our website. The webcast is being recorded and will be available for replay on our website approximately two hours after we conclude. Before we begin, please note that some information that you will hear or be provided with today consists of forward-looking statements within the meaning of the Securities and Exchange Act of 1934.
Such statements express our expectations, beliefs, and intentions regarding the future and include statements concerning our anticipated financial results, plans and expectations regarding the continuing development, commercialization, and financing of our fuel cell technology, our anticipated market opportunities, and our business plans and strategies. Our actual future results could differ materially from those described in or implied by such forward-looking statements because of a number of risks and uncertainties. More information regarding such risks and uncertainties is available in the Safe Harbor statement, in the slide presentation, and in our filings with the SEC, particularly the risk factor section of our most recent Form 10-K and any subsequently filed quarterly reports on Form 10-Q.
During this call, we will be discussing certain non-GAAP financial measures, and we refer you to our website, our earnings press release, and the appendix of the slide presentation for the reconciliation of those measures to GAAP financial measures. Our earnings press release and a copy of today's webcast presentation are available on our website under the Investor relations tab. For this call, I am joined by Jason Few, our President and Chief Executive Officer. Following our prepared remarks, the leadership team will be available to take your questions. I will now hand the call over to Jason for opening remarks. Jason?
Jason Few
Thank you, Mike, and good morning, everyone. Thank you for joining us today. I am pleased to welcome you to our third quarter fiscal year 2026 earnings call. In the third quarter, we took an important step in the commercial development of FuelCell Energy's data center strategy. The rapid growth of AI and high-density computing is creating power requirements that the existing grid cannot address quickly enough. For data center customers, access to power has become a critical constraint on development. The AI economy will not be constrained by silicon. It will be constrained by access to electricity. We believe distributed generation will become an essential layer of AI infrastructure, enabling the grid to expand while allowing AI factories to deploy on commercial timelines rather than utility timelines.
Our FuelCell Energy Blocks are designed to address the constraint by providing clean, continuous, behind-the-meter power that can be deployed at the customer site and scaled as demand grows. In the third quarter, we began to convert that value proposition into commercial commitments. We secured our first order for FuelCell Energy Blocks to supply baseload power for data center applications, increased committed backlog to $1.3 billion, and added $2.4 billion of awarded capacity backlog, resulting in total committed and awarded capacity backlog of $3.6 billion as of July 31. Awarded capacity backlog is a new category reflecting multi-phase contracts and capacity reservations, which I will let Mike detail in his remarks. Subsequent to the quarter end, we closed a 75 MW capacity reservation agreement with a major colocation data center operator for a Texas project.
We believe our utility-scale distributed generation platform is uniquely positioned to help accelerate AI infrastructure by reducing time to power, extending the existing electric grid with reliable behind-the-meter generation, and addressing many of the permitting and community challenges associated with large-scale power development. We expect to provide additional detail upon execution of definitive agreements. That is the central message for the quarter. We are moving from a growing pipeline to tangible commercial commitments while advancing the manufacturing capacity and operating capabilities required to deliver at scale. At the outset, I want to talk about this commercial commitment. During the quarter, we signed a capital equipment purchase agreement with Fit Energy to supply power solutions for data center applications. It covers up to 380 MW across four phases, sized to the customer's deployment schedule.
We received an upfront deposit on the initial 30 MW phase, which we expect to begin delivering in the fourth quarter, and the remaining phases are at Fit Energy's election. At the same time, our fiscal 2026 year-to-date pipeline has grown to roughly 10 GW of active proposals, and it reflects our progress toward proving our value proposition for data centers, which now accounts for about 97% of the total third quarter pipeline. I have said before that pipeline is a leading indicator, not a result, and I hold to that. The measure that matters is conversion, and Fit Energy is commercial proof that FuelCell Energy Block System can be the solution to some of the current public perception challenges facing data centers by providing scalable, clean, quiet, behind-the-meter power for data centers. The most important signal isn't that our pipeline is larger, it's that customers are buying differently.
AI has made power availability a strategic decision rather than simply a utility decision. In addition to our domestic backlog, we continue to execute on our existing global projects. In the third quarter, we successfully completed the repowering of the 42-modules Gyeonggi Green Energy project in South Korea. This execution demonstrates our capability to manage complex utility-scale repowering projects overseas while maintaining strict operational standards. Furthermore, it validates our long-term technology replacement cycle, proving that our existing fleet represents a continuous source of service and product revenues as Energy Blocks reach their natural replacement intervals. Important to converting our existing pipeline and backlog is our ability to scale, because demand only matters if we can meet it. To support our increasing backlog, we are systematically expanding our manufacturing capacity.
We are actively expanding our Torrington, Connecticut manufacturing facility to support the multi-megawatt demand of the AI factory and data center markets. Our immediate operational milestone is to increase our annualized production rate at Torrington to its current full capacity of 100 MW, with achievement of this milestone expected in October 2026. This near-term target represents a vital step toward our larger, long-term goal of reaching 500 MW of annualized production capacity by June 2028, an expansion we are already investing in. This expansion is progressing on schedule. During the third quarter, we finalized the comprehensive factory design, made significant equipment purchase commitments, and began the installation of a new high-volume tape caster that will dramatically increase our throughput. It is important to emphasize that this expansion is fully funded.
We are executing this capital spend in alignment with our committed backlog to ensure disciplined capital allocation with the goal of meeting the high volume requirements of global hyperscalers without building ahead of the market. As we scale, one aspect of our fuel cells has come into particular focus, and that is the sourcing strategy for our materials. Our carbonate platform provides a powerful supply chain advantage, and it does not rely on rare earth minerals and is scandium-free, utilizing globally abundant commodity metals like nickel and steel rather than highly volatile, critical minerals, or those that are predominantly mined in potentially sanctioned countries. Our platform was designed around the abundant industrial materials, not scarce critical minerals.
With over 90% of our supply chain sourced domestically in the United States and approximately 93% of our FuelCell Energy Block components reusable or recyclable through a take-back program, we offer our customers unmatched supply security in the current uncertain geopolitical environment. Along with growing demand for FuelCell Energy power systems, our technology is being validated on a global stage by an increasingly diverse group of world-class blue-chip partners. We are proud to report that we have delivered and installed the first two carbonate fuel cell carbon capture modules at ExxonMobil's Rotterdam complex in the Netherlands. This delivery represents a pivotal operational milestone under our joint development agreement with ExxonMobil Technology and Engineering Company. This installation is the world's first industrial-scale demonstration of our jointly developed carbon capture technology, successfully moving it out of the laboratory and into a real-world application, addressing hard-to-abate, low CO2 emissions from an industrial facility.
This Rotterdam demonstration is expected to validate our fuel cells performance under commercial operating conditions, positioning us as an essential technology partner for global industrial decarbonization. During the third quarter, we also signed a memorandum of understanding with Siemens to design and supply the electrical balance of plant systems for our fuel cell installations. The primary goal of this collaboration is to accelerate physical deployment and lower the cost of large-scale commercial projects exceeding 100 MW. We plan to jointly develop integrated distributed energy systems that combine our clean fuel cells with battery energy storage, advanced microgrid controls, and medium voltage electrical equipment. By optimizing the electrical balance of plant, we can manage the full spectrum of power variability from minutes down to microseconds.
We believe this integrated solution to be developed in collaboration with a global leader would provide the electrical reliability required to support critical, high-density AI data center workloads. The opportunity in front of FuelCell Energy continues to grow. Our responsibility is straightforward: execute. We are focused on converting commercial demand into contracted backlog, scaling manufacturing with discipline, and delivering for our customers. Those are the measures by which we should be judged, and they will remain our priorities as we work to build long-term shareholder value. With that, I'll turn the call over to our Chief Financial Officer, Mike Bishop, to provide a breakdown of our financial performance.
Michael Bishop
Thank you, Jason. Today, I will walk through our third quarter fiscal 2026 financial results, which demonstrate our robust capital position alongside a transitional period for our top-line revenue. Total revenue for the third quarter of fiscal 2026 was $33 million, a 29% decline compared to $46.7 million in the third quarter of fiscal 2025. Breaking this total down, products revenue was $18 million, down from $26 million in the prior year quarter. This reflects fewer module deliveries to South Korea as we completed the repowering of Gyeonggi Green Energy Fuel Cell Park, delivering all 42 modules committed under that program since 2024. Service revenue was $2.4 million compared to $3.1 million a year ago.
Generation revenue was $8.8 million, down from $12.4 million, driven principally by lower output from plants in our generation portfolio, including our 7.4 MW Groton Project, which was out of service for the full quarter pending a planned upgrade that we expect to complete in fiscal 2027. Finally, advanced technology contract revenue was $3.8 million compared to $5.3 million in the third quarter of fiscal 2025. We recorded a gross loss of $24.5 million in the third quarter of fiscal 2026, compared to a gross loss of $5.1 million in the third quarter of fiscal 2025. The primary driver was $17 million of charges recorded during the quarter, consisting of approximately $4 million to reduce the carrying value of certain inventories to net realizable value and approximately $13 million for losses on firm purchase commitments.
Both were recorded in connection with Phase Zero of our capital equipment purchase agreement, or CEPA, with Fit Energy, due to the fact that our current product costs and manufacturing overhead exceed the contractual pricing established under that agreement. We operated at an annualized production rate of approximately 37 MW during the quarter, which remains below the volume at which we expect our cost structure to align with market-based pricing for orders of this scale. These charges are expected to be limited to identified inventory and purchase commitments for Phase Zero and do not reflect our expectations regarding the overall economic value of the agreement. Loss from operations was $46.7 million, a 51% decrease compared to an operating loss of $95.4 million in the third quarter of fiscal 2025.
That improvement was primarily driven by the absence of the asset impairment and restructuring charges that heavily impacted the prior year period. Net loss for the quarter was $45.3 million compared to $91.9 million in the comparable prior year period, and net loss attributable to common stockholders was $45.3 million or $0.64 per share, compared to $92.5 million or $3.78 per share in the prior year quarter. Per share improvement also reflects a higher weighted average share count of 70.4 million shares following our equity issuances over the past 12 months. On a non-GAAP basis, adjusted EBITDA was -$36.7 million compared to-$16.4 million in the third quarter of fiscal 2025. That variance was primarily driven by Phase Zero charges I just described, which are not added back in our adjusted EBITDA reconciliation, rather than by any structural degradation in our core operating model.
Turning to our commercial progress, we are encouraged by the substantial expansion and evolution of our backlog. As of July 31st, 2026, total committed and awarded capacity backlog was $3.6 billion, a significant step change. We have structured our commercial backlog into two distinct categories to give investors clearer visibility: committed backlog and awarded capacity backlog. Committed backlog, which represents definitive, non-cancellable agreements executed by the company and its customers, was $1.3 billion, up approximately 4.1% year-over-year. Awarded capacity backlog was $2.4 billion. Awarded capacity backlog represents commercial awards and capacity reservations where we have been selected as the supplier and the parties are advancing towards execution of definitive agreements.
For the third quarter, this category is driven by the 350 MW across phases one, two, and three of our CEPA with Fit Energy, which was executed in June and provides for up to 380 MW in total product, commissioning, and service agreements, including the committed 30-MW Phase Zero. Fit Energy may elect to proceed with phases one, two, and three at its sole option, and no payment obligation arises with respect to a phase until Fit Energy makes an election to proceed with that phase. I want to be clear that awarded capacity backlog is not contracted firm order backlog or a guarantee of future revenue. Amounts may not convert to committed backlog or to revenue in whole or in part, and the timing and amount of any conversion may differ materially from our current estimates. We continue to maintain tight fiscal controls across the company.
As summarized on slide 19 of the presentation, total operating expenses for the third quarter of fiscal 2026 were $22.2 million, compared to $90.2 million in the third quarter of fiscal 2025. Looking at the details, administrative and selling expenses were $13.6 million for the quarter. Research and development expenses were $8.5 million for the quarter as we continue to invest in key product initiatives to support growth of data center opportunities. This year-over-year reduction in operating expenses was primarily driven by the absence of $68.5 million of asset impairment and restructuring charges incurred during the third quarter of fiscal 2025. Excluding those one-time historical charges, recurring operating expenses were essentially flat year-over-year, with a modest reinvestment in research and development offsetting lower administrative and selling costs. Now turning to the balance sheet and liquidity discussed on slide 21.
We ended the quarter with the strongest cash position in our history. Total cash equivalents, and restricted cash as of July 31st, 2026 was $737.3 million, up from $440.9 million at April 30th, 2026, the end of the prior quarter. Unrestricted cash and cash equivalents represented $658.1 million of that total, with the remaining $79.2 million in restricted cash and cash equivalents pledged as collateral for performance security and letters of credit. Our capital structure also remains straightforward. We carry no corporate convertible or high-yield debt, and our $153.6 million of total debt and finance obligations primarily consist of project-level financing, Export-Import Bank working capital facilities supported by our Korean deliveries, and sale leaseback obligations. This substantial capital buffer means that our manufacturing capacity expansion at our Torrington, Connecticut facility is fully funded.
We estimate the total requirement to expand Torrington to 500 MW of annualized production capacity to be between $200 million and $275 million, with completion targeted for June 2028. The expansion is backed by approximately $298 million of net proceeds raised from sales of common stock during the quarter, consisting of $245.5 million from our July underwritten offering and $52.9 million under our open market sale agreement. Looking ahead, we believe our strength in balance sheet and backlog expansion have established a clear path toward midterm profitability. We are now targeting achieving positive adjusted EBITDA results in the fourth quarter of fiscal year 2027. We believe this target is supported by a series of operational and commercial catalysts.
First, we have begun to increase our annualized production rate with the goal of achieving targeted annualized production rate of 100 MW in October 2026, up from approximately 37 MW this quarter, which should drive operating leverage over time. Beyond that, reaching our adjusted EBITDA target will depend on several key factors, including conversion of our awarded capacity backlog into definitive revenue-generating committed contracts, alignment with customer delivery schedules, and continued execution of our manufacturing cost reduction initiatives as we benefit from higher procurement volumes. There can be no assurance that we will achieve these production rates, the conversion of awarded capacity backlog, or the anticipated cost reductions within the timeframe currently expected.
In closing, we are executing our strategy with financial discipline, a fully funded manufacturing capacity expansion plan, and a sales pipeline that has grown to approximately 10 GW in fiscal 2026 proposals, which we believe positions us to drive long-term value for our shareholders. Thank you for your continued support, and I will now hand the call back to the operator to open the line for Q&A.
Operator
Thank you. The floor is now open for questions. If you have dialed in and would like to ask a question, please press star one on your telephone keypad to raise your hand and join the queue. If you would like to withdraw your question, simply press star one again. If you are called upon to ask a question and are listening via loudspeaker on your device, please pick up your handset and ensure that your phone is not on mute when asking your question. We do ask for today's session that you please limit yourself to one question and one follow-up. Your first question comes from the line of Julien Dumoulin-Smith of Jefferies. Your line is open.
Ivana Ergovic
Oh, hi. Good morning. It is actually Ivana Ergovic for Julien. Thank you for the time. I just had a question related to this deal announced in the 75 MW. If you could maybe give some more details in terms of the timeline and any potential opportunities for expansion versus that deal. I think that, yeah, that would be my first question. Thank you.
Jason Few
Hey, thank you, and thanks for joining us this morning. Yeah. After the quarter or subsequent to the end of the quarter, we closed the 75 MW capacity reservation agreement for a major data center operator. We have not disclosed the timing of that, but we anticipate not only that opportunity, but follow-on opportunities with the same customer. As you have seen, in particular in certain markets and including a market like Texas, where there is movement toward requiring bringing your own power. Our platform certainly sets up well to meet that requirement in Texas, and so we are excited about the opportunity. We are working through the definitive agreement, and that will really align the timeline from a delivery and execution standpoint.
We see this as a continuation or how the business model is really evolving to put capacity reservations in place as customers really look to line up power while they're completing their designs for the architecture of their data center and securing their commitments from their offtake customers as well. So, excited about this opportunity and look forward to executing.
Ivana Ergovic
Thank you. In terms of follow-up, I actually had a little bit of a different question. It's kind of related to your quarter results. There is a material increase in the cost of revenue, I guess, related to the Fit Energy deal. So, how should we think about it in the sense of the revenue recognition? I guess those would come with the deliveries in the fourth quarter and off that being basically the cost of revenue that you booked in this quarter. Is that the right way to think about it?
Michael Bishop
Sure. Ivana, this is Mike, and thanks for joining the call. I'll take that one. So as far as the Fit Energy Phase Zero, yes, we have disclosed that we do expect to begin recognizing revenue in that order in the fourth quarter of our fiscal year with the balance of it being completed in fiscal 2027. On the cost side, what you've seen come through this quarter related to that order is really our legacy cost structure. As we sit here today, the company's operating at 37 MW of production volume, which has the cost higher than current market rates. We expect that to normalize and be absorbed as we scale and get production rates up to 100 MW. As I said in my remarks, we do expect the company to get to adjusted EBITDA positive in the fourth quarter of fiscal 2027.
Ivana Ergovic
Okay, thank you. Can I just ask one more thing? In terms of the coming megawatts, it seems that you should be able to kind of start producing at those levels by the year-end?
Jason Few
Yes. I believe your question was, where is our production rate going? We have announced that we are scaling our production rate up to 100 MW by the end of the fourth quarter of this year. What that means is adding personnel, direct labor in our factory, as well as scaling our supply chain so that we are positioned to be able to deliver at that level as we get into fiscal 2027. In addition to that, we are adding manufacturing capacity as well to go up to 500 MW of total capacity in this factory by June of 2028.
Ivana Ergovic
Okay. Thank you very much. Thanks.
Jason Few
Thank you.
Operator
Your next question comes from the line of Manav Gupta of UBS. Your line is open.
Manav Gupta
Good morning. I wanted to focus more on the Exxon power project. It looks like your cells are delivered. I am just fundamentally trying to understand, are these two cells going to operate in a different way because their primary goal seems carbon capture? Can you help us understand how these two cells will be operating with Exxon, and what is the scope of expanding that partnership? Exxon is very bullish on carbon capture as a whole.
Jason Few
Manav, good morning, and thank you for joining the call, and thank you for the question. Yes, you are correct. The two modules have been delivered to Exxon at Rotterdam and are being installed. The primary focus of the application for those two modules is capturing carbon directly from the point source of emissions at the Exxon Rotterdam refinery or the Esso refinery, given that is the brand name they still use in Europe. We will demonstrate capturing 90+% of the carbon while simultaneously producing power, thermal energy, and hydrogen, which is a unique capability to our platform, not only as a fuel cell provider, but a unique capability in terms of other carbon capture technologies. The other big part of this demonstration, Manav, is to show our ability to capture CO2 from a low CO2 concentration stream of emissions, which is much harder to do.
That is another area where our technology accelerates in terms of our capability to actually capture low concentration CO2, which opens up the biggest aperture of market opportunity when you think across the industrial landscape. So everything from a company that does bottling and uses boilers to sterilize bottles, all the way to the refinery application we are demonstrating here in Rotterdam. We believe that demonstrating successfully our platform's capability, that that will open up an opportunity to expand this technology more broadly to address carbon capture across industrial applications globally. We think that there continues to be broad political support. If you look at the OBBA the actual incentives around Section 45Q actually improved. So we think that signals strong support, clearly strong support for carbon capture in Europe and Asia. The product will function differently from a core focus being carbon capture versus our power generation.
That being said, our core product and every product we ship today is carbon capture-ready. So we have the ability to also decarbonize power generation by capturing the CO2 from the fuel that we use to power our Energy Block. But the core focus in Rotterdam is carbon capture.
Manav Gupta
Perfect. My quick follow-up here is, in your opening comments, you talked about FuelCell Energy and the time to power advantage and how the grid is not scaling up. What we have also noticed is that there is obviously something called LCOE, but increasingly what the hyperscalers are finding out is by the time the electricity is delivered to you, it is not even close to LCOE, it is significantly higher. When you take that versus the benefits of on-site power generation, which is basically a spark spread, the cells actually start becoming a lot more economical and have a break-even of seven or eight years. I am just trying to understand from your perspective, can you also help us understand some of the other benefits of on-site power generation?
Because on the screen it might look the LCOE is cheaper, but by the time the power gets to the data center, it is actually a lot more expensive. If you could talk a little bit about that.
Jason Few
Sure. No, great question. I think if you look at the advantage of on-site power and LCOE, you are absolutely correct. If you look at what is really required to deploy new power generation in a constrained area, the amount of capital investment that has to go into that from an infrastructure upgrade on the utility side, which may include high voltage transmission, new local transmission, additional power electronics from transformers, et cetera, you can reduce a significant amount of that cost by doing on-site power generation.
Not only do you get a lower LCOE, higher reliability, you are also going to get the ability with our platform to integrate absorption chilling, so you can actually bring down the PUE of that data center, which is a core goal of a data center operator because they want to get more of the power to the compute, because that is really the business they are in is powering compute. The other big benefits are we offer a low noise solution and we can operate in water neutral. A lot of the things that communities are complaining about today, we address with our technology, including not contributing to poor air quality because although we use natural gas, we do not combust the fuel, which is another advantage.
You take all of those things together, I like to think about it more than just time to power, but it is really time to power on. Because it is the time to deliver it, can you get it permitted, which is a big challenge today, and our platform really addresses a lot of those concerns. Really time to power on, which is also time to revenue, and we think that creates a significant advantage.
Manav Gupta
Thank you so much.
Jason Few
Thank you.
Operator
Your next question comes from the line of Jason Tilchen of Canaccord Genuity. Your line is open.
Jason Tilchen
Good morning, and thanks for taking my questions. I guess to start, can you perhaps help us bridge the gap between the achievement of the 100 MW run-rate that you stated you expect at some point next month to the Q4 of fiscal 2027, updated target for reaching EBITDA profitability, and what some of the key factors, maybe expand on some of the key factors that you laid out in the press release that could help you achieve that rate. Thank you.
Michael Bishop
Sure, Jason. This is Mike. I will take that. As we said, we are hiring, we are ramping our supply chain to get our run-rate up to that 100 MW annualized run-rate in the fourth quarter of fiscal 2026, and targeting adjusted EBITDA positive in fourth quarter of fiscal 2027. Between now and then, the key factors that will drive that is, one, continuing to convert our awarded capacity into committed backlog. As we sit here today, we are executing on the 30 MW committed backlog from Fit Energy Phase Zero. We need to continue to convert that broader order as well as other opportunities, and of course, we talked about this new 75 MW capacity reservation agreement that was announced this morning. That is another opportunity there to continue to convert.
Converting backlog, lining up with customer schedules, and then, of course, continuing down the cost reduction curve as we expand and we scale in the factory. We will absorb overhead, and we will also get leverage from our supply chain. Those are the main drivers that will be occurring in the financial statements over the course of the next year plus.
Jason Tilchen
Okay. That is really helpful, and I guess the follow-up there is, in terms of those factors you laid out, some of those are in your control and some of them are at the discretion of the customers. Fit Energy has the option to proceed with these deals. So I am just curious, maybe if you could help us understand on the cost reduction side, if you feel like you are already or within close line of sight of achieving what you need to achieve to get to that point, and then what does the scenario look like where maybe Fit Energy is not ready to proceed with that phase in time to achieve it? What does the sliding scale look like, in that sense, if you are able to achieve some of those milestones but maybe not all of them?
Michael Bishop
So again, on the cost reduction side, we have been planning for this for a long time. We have a very well-defined cost reduction curve in front of us that we are executing on. On the commercial side, we talked about a 10 GW pipeline of opportunities. We are not just reliant on one or two customers. We see significant opportunities here across our customer base and fully expect to be able to convert additional pipeline into backlog over this time period.
Jason Tilchen
Okay. Really helpful, and maybe can sneak in one quick final one. I believe in the first question that was asked, it was around the bridge from 37 MW to 100 MW over the next call it six to eight weeks, and you mentioned adding labor and increasing the supply chain to get to that run-rate. Are those sort of boxes, have those been ticked already and it is just a matter of simply working through the next few weeks of just getting those people up and running? Or are you still in the process of finding that labor and making sure that that supply chain is at the right point?
Michael Bishop
Yeah. There is multiple elements there. But yeah, we have made considerable progress. We are hiring as we speak. We have added an additional shift in our factory, so you will see meaningful increase in our production rate come through this quarter as we described.
Jason Tilchen
Thank you very much.
Operator
Your next question comes from the line of Ryan Pfingst of B. Riley Securities. Your line is open.
Ryan Pfingst
Hey, guys. Thanks for taking the questions. Maybe just to start with a follow-up on the last one. For the target of positive EBITDA in fiscal full Q 2027, can you frame that in terms of what that reflects or where you expect to be from an annualized production rate perspective at that point?
Michael Bishop
Thanks for the question, Ryan. We would expect at least 100 MW of volume to support that, if not more. And again, that will be dictated to some extent by our customers in converting pipeline to backlog as well as customer delivery schedules, so being able to line up with our customer requirements. As we described, we will absolutely have the capability in Torrington to get above 100 MW. We are targeting 500 MW of capacity by June of 2028. That does not get turned on like a light switch. That will come online over time as we unlock constraints. One of the big constraints that we've talked about is tape casting. That process is well underway and will be installed in next fiscal year. That's a big unlock for us to create additional capacity.
Ryan Pfingst
Got it. On the Fit Energy deal, curious on your expectations for moving to the remaining phases. Do you see Phase 1 moving forward only after the initial phase is up and operating, or could that decision, in your view, come before then?
Jason Few
Ryan, this is Jason. No, they are not sequential, or certainly don't have to be sequential. The gating on those is just their ability to close out their agreements with their customer. That can happen at any time. It's not a complete the first 30 MW and then they'll move forward or consider Phase 1. They're not a sequential set of events.
Ryan Pfingst
Got it. That's helpful. Thanks, guys.
Jason Few
Thank you.
Operator
Your next question comes from the line of Noel Parks of Tuohy Brothers. Your line is open.
Noel Parks
Hi. Good morning. I noticed that with the updated CapEx guidance, it has actually been nudged down a bit for the fiscal year. I think there was a mention in the materials that some of that reflected equipment deliveries that would not be happening until after the fiscal year-end. I was just wondering if you could just elaborate a bit on that. I am assuming that would be deliveries primarily for the Torrington expansion.
Michael Bishop
Correct. Good morning, Noel. This is Mike. Good read. The previous disclosure that we had around expected CapEx coming through the cash flow statement in fiscal 2026 was $20 million-$30 million. We are now saying that that is $10 million-$20 million, just given timing. It is by no means a reflection of execution. It is really timing of receiving certain equipment based on our prior schedules. As we have described now, we are on track for the 500 MW expansion by June of 2028. We have committed $200 million-$275 million of capital to that. If you look at our purchase commitments disclosures, that is up significantly quarter-over-quarter, and reflecting not only the increase in production rate, but also capital commitments that will be delivered in future quarters.
Noel Parks
Great, thanks. Also early in the prepared remarks, or maybe it was right at the start of Q&A, there was a comment about your fuel cells, I guess the necessity of aligning with customer delivery schedules. I was just sort of thinking in this ramp-up period on one hand, and then you have new agreements in negotiation and coming online. Just thinking a bit about how you manage that, since it looks like you are going to be kind of in anything but a steady state sort of trend for the next few years.
Jason Few
Noel, this is Jason. The way that you can think about this is we have visibility into our production capabilities. We have visibility into our expansion capacity ramp. That information is closely tied to and fully understood by our business development team. When we are talking to customers about opportunities, and schedule always becomes part of the question or conversation ultimately, we make sure that the commitments that we are making align to our view in terms of our ability to meet and deliver against that demand. Even though you might sign an agreement for 100 MW of power, you really need to look at, well, what is the delivery schedule for that?
Because first power could be something as small as 20 MW, additional power comes on as they finish building out the data hall, or maybe as they add a second building for a second data hall. So you have to really look at the full build-out from the customer perspective. Then we make sure that we align our commitments to our confidence on our scale-up and manufacturing capabilities.
Noel Parks
Great. Thanks a lot.
Jason Few
Thank you.
Operator
Again, if you have a question, you just star one on your telephone keypad. Your next question comes to line of Chris Ellinghaus of Siebert Williams Shank. Your line is open.
Chris Ellinghaus
Hey, good morning, everybody. Mike, in your backlog slide, do you sort of envision adding more granular categories, sort of as you convert pipeline?
Michael Bishop
Good morning, Chris, and thanks for joining the call. So obviously, a big step change in our backlog disclosures this quarter compared to last quarter. We've added an additional category called awarded capacity backlog. What is in there as of July 31st 2026, the end of last quarter, is really the three phases of the Fit contract that aren't currently committed. So this is phases one, two and three.
Broken down between product and service. So we think we have a fair amount of disclosure there on the potential that will be converted into committed backlog. As far as additional categories, we would expect, and we talked about this 75 MW capacity reservation agreement, we would expect that to go into awarded capacity backlog as well, whether it's part of product or service or broken between the two. We'll disclose that in future periods. That's the expectation, kind of following industry practice these days, where folks are disclosing those reservations, whether they're called CRAs or something else, but really reservations on future capacity, which the company's being paid for. So we will be as transparent as possible as we add these additional opportunities into our backlog.
Chris Ellinghaus
Okay, thanks. Jason, I sort of liked the way you framed the pipeline versus conversion discussion. I don't know how to put this, but are there any timelines or way points for some of the pipeline that we might look for you to announce any kind of agreement out of the pipeline?
Jason Few
Sure. No, great question, Chris. Thank you for being on the call. The way you ought to think about it is, we talk about our sales pipeline, and the 10 GW we talked about today are tied to proposals that our business development team has, with customers, directly placed those proposals. When we talk about awarded capacity agreements, what we are talking about there is that we, along with the customer, have agreed to allocate manufacturing capacity in support of that customer's order. Along with that awarded capacity, there is a date certain in which we and that customer have agreed that we are going to get to the definitive agreement, and at that point, that awarded capacity would convert into our backlog, what Mike just talked about.
What you find in our backlog are things that are committed firm project orders, and that is the way we have reported backlog for probably the last six or seven years in terms of that backlog number. What you should really look for is the velocity in which we take awarded capacity and convert that into committed definitive agreements. But in each of those awarded capacity agreements, there is a timeline tied to getting to that definitive agreement. Again, what it gives the customer, the benefit for the customer is it reserves manufacturing capacity, right? It gives them the ability to complete their final designs from an architecture perspective in terms of everything from our Energy Block all the way to the rack and how they are going to do that, and to finalize their agreements with their customers.
It gives us better visibility into our planning, gives us the ability to make purchases on materials from a supply perspective, and there is financial consideration for providing that committed capacity reservation.
Chris Ellinghaus
Okay. That helps. Appreciate it.
Jason Few
Thank you.
Operator
With no further questions, that concludes our Q&A session. I will now turn the conference back over to President and CEO, Jason Few, for closing remarks.
Jason Few
Thank you, JL. Before we conclude, I want to leave you with this. The opportunity in front of FuelCell Energy is significant. AI and high-density computing are creating an urgent need for reliable, scalable power, and our technology is positioned to help meet that need. But opportunity alone does not create value. Execution does. Our focus is clear: convert awarded capacity and our pipeline into closed transactions, scale manufacturing with discipline, and deliver for our customers. We will align investment with commercial commitments, increase capacity responsibly, and scale to drive greater cost leverage across the business. Partnership will be central to that execution. Our collaboration with Fit Energy, Siemens, and the customers reserving manufacturing capacity demonstrates what is possible when technology, capital, industrial capability, and customer demand come together around a shared objective. These are not simply commercial relationships.
They are partnerships built to accelerate deployment, reduce execution risk, and create long-term value for everyone involved. We believe the market is moving toward us. Power has become a strategic constraint, and FuelCell Energy has the technology, manufacturing platform, and partnerships to help customers move from ambition to operation. Now we must execute with urgency, discipline, and consistency. Before we close, I want to thank the entire FuelCell Energy team. Your commitment, resilience, and focus makes our progress possible. I also want to thank our customers, partners, and shareholders for your continued confidence and support. We appreciate your time today and look forward to updating you on our progress next quarter. Thank you.
Operator
This concludes today's conference call. You may now disconnect.