VolumePre-market / after-hoursUnusual moveNotable move · hover or tap for why
Market Cap$4.79B
Open$6.60
Trailing P/E-27.73
Day Range$6.40–$6.99
Dividend Yield0.00%
52W Range$6.38–$13.96
EPS-$0.31
Volume7.33M
Avg Volume5.38M
50-Day Avg$8.41
200-Day Avg$10.35
Why is NXE moving?
NXE rose modestly as uranium stocks broadly gained (Cameco up ~3%), helped by positive drill results showing a 15% expansion of the high-grade PCE zone at Rook I.
Wall Street coverage of NexGen Energy (NXE) is thin, with just one rating on record, a 100% bullish (Strong Buy) consensus from JP Morgan. Analyst Bill Peterson initiated coverage on Sept. 21, 2026 at Overweight with a $14.00 price target. On Nov. 11 he maintained Overweight but trimmed the target to $12.00. Because there is only one analyst, the average, median, high and low targets are all $12.00, so there is no dispersion to gauge broader sentiment, and the consensus should be read with caution. The lower target, with the rating unchanged, suggests a modest valuation adjustment rather than a change in conviction. The long-term thesis looks supported by recent developments: Rook I construction is advancing, permitting has progressed, and the company reported a high-grade uranium expansion at Patterson Corridor East. Some commentary notes the shares already trade at a premium after a strong multi-year run.
▲ Bull caseRook I broke ground in June on the C$2.2 billion project, and a Red Cloud Securities site visit found work consistent with being on schedule and on budget. A build team that planned for years supports a first-production target of the third quarter of 2030.[8][7]
▼ Bear caseNo uranium is sold until the mine is built, so any delay or cost overrun hits a company with no revenue to absorb it. Construction financing remains unclosed, and first production is years away, leaving the second deposit undefined and execution risk elevated.[7]
▲ Bull caseWith about 96% of the reserve base unsold and contracts priced at delivery, each pound captures market prices, which recently hit $96 per pound, the highest since 2007. Output can flex between 3.5 and 30 million pounds, protecting returns in weak markets.[8][7]
▼ Bear caseOnly about 12 million pounds are contracted for the first five years, and analysts note prices may need to rise further to incentivize new supply. Short contracts priced off the market offer no revenue floor if uranium prices fall before the mine ships.[8][7]
▲ Bull caseAnalyst targets imply large upside, with a consensus Buy and an average target near $14.15, about 93% above the recent price. Shares trade near 52-week lows despite strong uranium fundamentals, which suggests a disconnect that could close as construction advances.[2][8]
▼ Bear caseTargets are being cut, with JPMorgan lowering its target from $14 to $12. Shares trade below the 200-day average, short interest is 8% of float and rising, and earnings are forecast to stay negative for three years, which undermines the case for a rerating.[6][4][9]
NexGen Energy shares closed higher, with the stock up 1.90% to $6.96 and flat after hours. The stock traded between $6.40 and $6.99 on above-average volume, rebounding from an early dip while the wider AI-led selloff pared losses into the close. Investors weighed the company's sixth annual sustainability report, which said Rook I construction is advancing after final federal approval, along with Tuesday's Patterson Corridor East drilling update. That update extended the high-grade zone 15% vertically to 739 m, and the overall footprint now stands at 905 m vertically. Stifel reiterated a Buy rating with a C$30 target, and consensus is Strong Buy. Uranium peers were choppy as the Monday nuclear rebound faded, and Kazatomprom's executive detentions added sector headline noise.
NexGen Energy released fifteen more drill holes from its Patterson Corridor East discovery, 3.5 km from the Arrow Deposit. The high-grade subdomain grew 95 m vertically to 739 m (+15%) and 28 m along strike to 238 m (+13%). The 2026 campaign has now lifted the overall footprint 29% vertically to 905 m. The results are exploration-stage and include no resource or economic figures. Assays are pending, and 31,480 m of the 42,000 m program is complete. Shares closed modestly higher and extended slightly in after-hours trading. Volume ran above average after an earlier intraday dip, so gains were choppy. The move followed a sharp uranium-sector rebound the day before, when Nvidia's CEO reinstatement lifted risk appetite after a steep sell-off. Supportive uranium backdrop: Korea Hydro's tender is up 50% with price caps removed, and spot is stable near $90/lb. Analyst sentiment is mixed: Morgans upgraded to Buy, while JPMorgan trimmed its target to $12 from $14.
NexGen Energy rebounded as uranium and nuclear names rallied with a broad AI-led market bounce after Nvidia reinstated Jensen Huang as CEO. Cameco rose about 7% and the Sprott Uranium Miners ETF gained about 6% intraday, while Energy Fuels' plan for a 1 million-pound White Mesa campaign added sector support. Uranium equities have been trading with AI sentiment, and the Sprott fund was down 57% from Jan. 28 to Nov. 19 even as UxC's long-term uranium price rose to $97/lb. India and Canada's 10-year, $2.6B uranium supply deal, announced with Cameco as the supplier, added to the backdrop. NexGen shares closed up 5.62% at $6.77 on volume above average, and were up another 0.78% after hours. RBC trimmed its price target to C$18 (Outperform) last week, and short interest sat near 8% of float at the end of October. The broader energy sector fell, with XLE down on lower oil prices.
NexGen Energy shares fell and closed near a new 52-week low as uranium developers stayed under pressure from weak equity-market sentiment and financing concerns, despite constructive commentary on Rook I. RBC reaffirmed an Outperform rating after investor meetings, citing construction progress, a reiterated C$2.2B capex estimate and a 2030 first-production target. It cut its target by C$2 to C$18 on 'broad sector compression'. Management is targeting a funding plan by H1 2027, with liquidity seen lasting through Q3 2027. Q3 results also showed a wider-than-expected loss, and JPMorgan trimmed its target to $12 earlier this month. Shares fell 4.81% to $6.93 on volume well above average, then edged up 0.29% after hours. The IEA's bullish nuclear and electricity-demand outlook did little to offset the pressure.
NexGen Energy remains under pressure near its 52-week low as uranium equities stay weak despite supportive long-term fundamentals, with spot uranium near US$91/lb and long-term contract prices at record highs. Investors are weighing a larger-than-expected Q3 loss, JPMorgan's target cut to $12 from $14, and an average analyst target trimmed to about $14.15, though ratings stay overwhelmingly Buy. Shares closed slightly lower on heavy volume, about double average, after trading between $7.13 and $7.57. They were little changed after hours. Construction at Rook I is reported on schedule and funded through late 2027, and sector sentiment is being shaped by financing worries for developers and Cameco's production shortfall.
NexGen Energy shares closed lower in a weak uranium tape, with investors weighing a post-earnings reset: Q3 results narrowed the net loss to C$22.3M, management said Rook I construction is on schedule and on budget, and funding runs through Q3 2027 with financing for the bigger spend still to be detailed. JPMorgan trimmed its price target (to C$17 from C$20-ish equivalent $12 from $14) while keeping Overweight, and TD Cowen reiterated Buy with a C$20 target. Uranium equities remain deeply out of favor despite physical prices near $90/lb, and Cameco trimmed 2026 output guidance, while the broader energy sector edged higher. Shares closed down 1.40% at $7.76, edging up about 0.6% after hours.
NexGen Energy shares closed little changed as investors weighed a constructive Q3 construction update against a wider-than-expected loss and a JPMorgan price target cut to $12 from $14 (Overweight…
NexGen Energy shares rallied as uranium equities rebounded broadly, with Paladin and Boss Energy up over 10% in Australia and reports of heavily shorted positions unwinding.
NexGen Energy shares rebounded as nuclear and uranium names bounced after a brutal tech-led selloff, with peers such as Cameco, Denison and Uranium Energy also higher.
NexGen Energy was little changed in a volatile session, with investors positioning ahead of its third-quarter results, expected after the close (consensus roughly a $0.02–0.03 per-share loss).
NexGen Energy shares steadied and closed modestly higher, edging up as investors positioned ahead of Wednesday's third-quarter results, where analysts expect a loss of about 3 cents per share.
NexGen Energy shares closed lower as uranium equities stayed under pressure ahead of the company's quarterly results, expected after the close on November 3, with analysts looking for a loss of about…
NexGen Energy shares fell as uranium equities were pressured by Cameco's third-quarter earnings miss (adjusted EPS well below consensus after an extended Key Lake outage, narrowed 2026 production…
NexGen Energy retreated as uranium developers gave back part of the prior session's gains, with investors weighing Rook I financing, which reportedly involves a roughly $1 billion raise and talks…
NexGen Energy shares closed modestly higher as investors weighed Rook I construction progress and financing questions against a supportive uranium backdrop.
NexGen Energy shares rallied as uranium names led a risk-on tape, with the uranium group among the strongest industry groups (about +3.4% in one heatmap) while the broader energy sector fell roughly…
NXE gained 5.6% to close at $6.77, opening 8.6% above the prior close. Intraday range of $0.32 ($6.75 – $7.07) spanned 4.7% in a volatile session.
+5.6%
Nov 20, 2026
Sharp DropNew 52-Week Low
NXE fell 7.5% to close at $6.41. Intraday range of $0.49 ($6.38 – $6.87) spanned 7.7% in a volatile session. Volume reached 10.63M shares (1.7× the 20-day average). Set a new 52-week low of $6.38. Closed near the day's low as sellers pressed into the close.
-7.5%
Aug 28, 2026
Sharp Drop
NXE fell 7.1% to close at $10.40. Intraday range of $1.01 ($10.28 – $11.29) spanned 9.8% in a volatile session. Closed near the day's low as sellers pressed into the close.
-7.1%
Jun 5, 2026
Sharp DropGap Down 2.7%
NXE fell 9.9% to close at $10.28, opening 2.7% below the prior close. Intraday range of $0.88 ($10.27 – $11.15) spanned 8.6% in a volatile session. Closed near the day's low as sellers pressed into the close.
-9.9%
Jun 3, 2026
Sharp Drop
NXE fell 8.8% to close at $11.34. Intraday range of $0.96 ($11.34 – $12.30) spanned 8.5% in a volatile session. Closed near the day's low as sellers pressed into the close.
-8.8%
Jun 2, 2026
Big Rally
NXE gained 9.1% to close at $12.44. Intraday range of $1.20 ($11.30 – $12.50) spanned 10.6% in a volatile session. Volume reached 9.84M shares (1.6× the 20-day average). Closed near the session high, with buyers in control into the close.
+9.1%
Apr 22, 2026
Big Rally
NXE gained 7.6% to close at $13.10. Intraday range of $0.74 ($12.36 – $13.10) spanned 6.0% in a volatile session. Closed near the session high, with buyers in control into the close.
+7.6%
Mar 3, 2026
Sharp DropGap Down 4.9%
NXE fell 7.1% to close at $12.36, opening 4.9% below the prior close. Intraday range of $0.90 ($11.76 – $12.66) spanned 7.7% in a volatile session. Recovered from the lows into the upper part of the range as dip buyers stepped in.
-7.1%
Feb 4, 2026
Sharp Drop
NXE fell 7.3% to close at $11.62. Intraday range of $1.44 ($11.13 – $12.57) spanned 12.9% in a volatile session.
-7.3%
Jan 28, 2026
Big RallyNew 52-Week High
NXE gained 8.9% to close at $13.92. Intraday range of $1.09 ($12.87 – $13.96) spanned 8.5% in a volatile session. Volume reached 17.59M shares (2.4× the 20-day average). Set a new 52-week high of $13.96. Closed near the session high, with buyers in control into the close.
+8.9%
Jan 2, 2026
Big RallyNew 52-Week HighGap Up 2.6%
NXE gained 11.4% to close at $10.25, opening 2.6% above the prior close. Intraday range of $0.95 ($9.42 – $10.37) spanned 10.1% in a volatile session. Volume reached 13.14M shares (1.8× the 20-day average). Set a new 52-week high of $10.37. Closed near the session high, with buyers in control into the close.
+11.4%
Dec 19, 2025
Big Rally
NXE gained 7.4% to close at $9.13. Intraday range of $0.77 ($8.50 – $9.27) spanned 9.1% in a volatile session. Volume reached 18.31M shares (2.4× the 20-day average). Closed near the session high, with buyers in control into the close.
The analysis sees Arrow’s grade and potential low costs as a strong asset advantage, but emphasizes that NexGen’s single-project exposure, construction spending, and funding gap could require further financing and dilution; the specific rating is members-only.
Argonaut’s constructive uranium-market thesis favors NexGen as a developer, arguing that rising demand and constrained supply support uranium prices and that the market does not fully price Rook I’s development potential. It assigns NexGen a Speculative Buy and A$20.50 target, supported by sector forecasts and company-specific valuation analysis.
Culper discloses a short position and argues that Rook I’s value and production forecasts are overstated, citing its analysis of high-grade zones, dilution, costs, and construction timing. It estimates substantially lower project value under its scenarios and concludes that NXE shares face downside.
Argonaut identifies NexGen as a preferred uranium developer, arguing that Rook I’s scale and the sector’s supply-demand outlook support potential value upside, including possible M&A interest. Its report includes NexGen valuation sensitivities and a Speculative Buy rating with an A$20.80 target.
Argonaut updates its Patterson Corridor East model to estimate 62 million pounds at 1.87% U3O8, citing new high-grade drilling and potential for further deposit growth. It maintains Speculative Buy and raises its target to A$17.40.
Argonaut views NexGen’s roughly A$1 billion capital raise as funding for Rook I advancement and as evidence of investor appetite, while noting permitting and potential M&A catalysts. It maintains Speculative Buy and raises its target to A$16.50, using a blended spot and forecast uranium valuation.
Latest earnings analysis · Q3 FY2026 · Nov 10, 2026
Rook One construction is on schedule, on budget and to scope after the Aug 13, 2026 groundbreaking. The airstrip expansion and key pads are done, the shaft sinking contractor is mobilized, and the freeze plant arrives January 2027, with temporary freezing in March 2027. Shaft excavation starts at the beginning of Q3 2027. First concrete pour is scheduled for Dec 16, 2026, and over 50 process plant long-lead items are in procurement.
Liquidity was CAD$822 million in cash and short-term investments, plus CAD$341 million of U3O8 inventory that will not be sold to fund the project. Management says it is funded through the end of Q3 2027. Larger cash drawdown starts with shaft sinking, and 2027 is still expected to be peak CapEx (an analyst estimated roughly CAD$600 million, and management confirmed 2027 as the peak year).
Financing will likely combine several options, including prepayments (in negotiation with entities in and outside the US), strategic financing and project financing. Any prepayment must preserve leverage to the uranium price at delivery. The shaft sinking contract is signed and came in line with the August 2024 feasibility cost estimate. Cost per pound remains just under US$10 cash and about US$14 all-in, and G&A is expected to fall as a percentage of spend into 2027.
Uranium market: the long-term price held at a record US$99 per pound as of Oct 31, with 3- and 5-year forward prices at US$105 and US$112. Management cited over 88 GW of nuclear capacity under construction and about 8 GW more from restarts and uprates. Utilities, including Asian ones, are concerned about supply from 2030 onward, and the US midterm elections have not changed contracting conversations. Nexgen is in advanced talks with many utilities and expects additional sales agreements in coming periods, with short-duration contracts priced at market at the time of delivery.
At Patterson Corridor East, 3.5 km from Arrow, the high-grade subdomain grew 17% to 644 meters in the quarter, and a fifth drill rig was added. More results are expected imminently, and the core yard is being expanded for the 2027 drill campaign. An initial resource estimate is targeted around the start of Q3 2027, subject to assay timing. Engineering, environmental studies and permitting would still be required.
Thank you for standing by. This is your conference operator. Welcome to the NexGen Energy Third Quarter 2026 Results Conference Call. As a reminder, all participants are in listen-only mode, and the conference is being recorded. After the speaker's remarks, there will be a question-and-answer session at the end. To join the question queue, you may press star then one on your telephone keypad. You will hear a tone acknowledging your request. Should you need assistance during the conference call, you may signal an operator by pressing star then zero. I would now like to turn the conference over to Mr. Leigh Curyer, Chief Executive Officer and Founder with NexGen Energy Limited. Please go ahead, sir.
Leigh Curyer
Thank you, Jason. Good morning, and thank you to our shareholders and stakeholders for joining NexGen Energy's Q3 2026 Financial Results and Investor Conference Call. Joining me today is Travis McPherson, Chief Commercial Officer, Ryan Podrasky, Chief Financial Officer, and Chris Copley, Project Director. During today's call, the latest on our commercial activities, including the uranium market environment during the third quarter of 2026 and to date, the continued exploration success at Patterson Corridor East, or PCE, only 3.5 km to the east of Arrow, and importantly, an update on the successful construction progress at our Rook I site, including a slideshow highlighting the advancement at site. Then we'll move into the Q&A portion of the call, where you'll have the opportunity to ask myself, Travis, Ryan, and Chris any questions.
We'll be making forward-looking statements throughout the call today, so please visit our website for all the relevant disclaimers. August 13, 2026, will stand as a defining day in NexGen's history. On that day, we held a ceremonial groundbreaking for the Rook I project, symbolizing the commencement of major post-approval construction activities. August 13 was 12 years and six months from the initial discovery of the Arrow deposit. This journey has been defined by the courage to test common geological convention, perseverance, resilience, genuine collaborations and partnerships with local communities, underpinned by rigorous planning, delivery of those stated objectives with elite safety and respect for the environment in which we conduct our operations. Simply, this approach, which never stops, has delivered better than the past.
The solid foundation of NexGen, built on delivery over the past 16 years, is today being directly reflected on the quality of work on the ground in the successful execution of construction at Rook I. The people who have stood alongside of us and shared their perspectives on August 13 at the groundbreaking ceremony all reflected what this project means. Saskatchewan's Premier, Scott Moe, former Prime Minister Stephen Harper, Secretary of State Buckley Belanger, Métis Nation–Saskatchewan President Glen McCallum, Métis Local 39 President Keith Shewchuk, and leaders and members from all four of our local priority area communities, many of our international shareholders, board of directors, team members, among many others, some of whom were absent due to illness or family commitments. Their presence spoke to something larger than a single mine.
Rook I is a provincial priority, a national champion, and is being delivered in partnership with the local communities to set a new standard across the global resources sector. Rook I and the southwestern section of the Athabasca Basin is the foundation of nuclear fuel supply for the world, underpinning the trajectory of Northern Saskatchewan and Canada's nuclear energy objective for decades to come. That time could not be more important than it is today. The uranium market is at unprecedented levels of demand and challenged supply. The long-term uranium price reached and has maintained its historical high during the quarter at $99 per pound, and forecast to go considerably higher by the market observers. The world's existing producing mines are dominated by production downgrades, rising sustaining capital, and increased costs of production as they move into the latter stages of mine life.
Two forces are defining this era, energy security and electrification, and they point in the same direction. We need more power, and it needs to be sovereign. The idea that Canada has what the world needs has taken on greater significance, most recently echoed by Prime Minister Mark Carney. From a resource perspective, and particularly uranium, that is certainly true. Having the resources is only one component. Realizing Canada's opportunity depends on companies who recognize the opportunity, where the uranium market is heading tomorrow, not where it has been in the past, and responsibly executing.
There is a new breed of future uranium producers in Saskatchewan, and at a time of unprecedented market opportunity, and full credit to our cohort of uranium companies with projects under construction as we speak, who in these inflationary times are structuring contracts with the same approach as NexGen, tied to prices in the future at the time of delivery, in order to mitigate inflation and cost increase risk, whilst being financially astute, focused on maximizing financial returns for shareholders and maximizing royalties for the great province of Saskatchewan. Yes, uranium prices have risen five times over the past decade, yet we are mining the same amount of uranium as we were 10 years ago. Prices simply will rise substantially higher due to increasing costs of production and the depletion of the existing mines. Momentum across the nuclear sector continues.
Over 88 GW of nuclear capacity is now under construction, with approximately 8 GW more from restarts and uprates. That is over 20% growth, and that does not take into account the massive backlog of planned reactors, as well as SMR deployments, which are making rapid advancements. This growth, which the industry has not seen since the 1970s and 1980s, is being driven by the requirements of nations around the world to have reliable base load power at scale to meet rapidly rising electricity demand. These massive investments in global energy infrastructure are happening right now. In Canada specifically, we have seen a massive resurgence in the demand for new nuclear power plants, including Saskatchewan, where Premier Scott Moe announced plans for 2.6 GW of nuclear power in northern Saskatchewan by 2050.
Further, we are seeing the federal government of Canada revitalize and recommit to the Canadian nuclear stalwart, CANDU, promising to export this homegrown proven technology around the world. It's an incredible situation developing in Canada. During the quarter, Prime Minister Mark Carney pitched the project, a four-reactor nuclear plant at Darlington, Ontario, funded by a CAD 3 billion federal and provincial investment, as part of Canada becoming master of its own destiny. A new chapter in Canada's nuclear history is being written. As Prime Minister Mark Carney stated, "We are an energy superpower, and we are only getting stronger." Across Canada, nuclear power is having its moment. In Port Hope, Ontario, the provincial utility has proposed a new 10,000 MW nuclear station, while on the shores of Lake Huron, one of the world's largest nuclear plants, the Bruce Power Nuclear Power Plant, is advancing to double the plant's output to 4,800 MW.
In Alberta, a proposal to generate a similar amount of power via four large-scale reactors near the town of Peace River has begun its impact assessment process. While in New Brunswick, home to the only operating nuclear plant outside of Ontario, the province is investigating ways to expand nuclear. This momentum was also evident at the industry's preeminent uranium conferences during the quarter, including the World Nuclear Symposium in London and the Global Uranium Conference in Adelaide, where strong interest in NexGen's offtakes and supportive sentiment reinforced the highly constructive backdrop for NexGen and the uranium industry at large. This shift is increasingly tangible, with major technology companies like Amazon, Microsoft, Meta, Google, and many others financially backstopping the expansion of nuclear power and the supply chains required to support this growth.
Further, governments are signaling the need for strategic reserves, Kazakhstan being the most recent during the quarter, and increasing investment in nuclear fuel supply chains. Together, these trends continue to strengthen expectations for materially higher uranium requirements. These dynamics are evident in uranium pricing today. As mentioned earlier, as at October 31, the term pricing is at a historical high, $99 a pound. Three and five-year forward prices have reached 105 and 112 dollars US per pound respectively. Uranium prices continue to rise higher, highlighting the strength of the fundamentals in our sector. Our Rook I project is one of only a couple of uranium projects globally under construction today. Together with Patterson Corridor East and our 190,000 hectares of prospective land, NexGen's foundation to the uranium required for the next phase of global nuclear growth. At Patterson Corridor East, the 2026 drill program is nearing completion.
We are seeing continued growth and strength of the mineralized system, with more to come. Results published during the quarter once again highlighted a significant basement-hosted uranium system that continues to grow. During the quarter, the high-grade subdomain expanded by 17% to presently 644 meters, and given results, allocated an additional fifth rig to the program. More results will be received and released imminently. While subsequent resource estimation, engineering, environmental studies, and permitting will be required, these results are pointing to PCE as a highly advantageous avenue for NexGen and Canada's nuclear energy objectives. On contracting, we are in advanced discussions with many utilities around the world. Global utilities recognize NexGen's unique value proposition in terms of materially diversifying their supply chains to reliable, technically sound, and geopolitically stable new sources of uranium. We will continue to advance negotiations and forecast executing additional sales agreements in the coming periods.
As we deliver construction of the Rook I project, our contracting strategy is simple and remains the same: to realize the most value per pound produced with every pound that is produced and sold by shortening contract durations, tying them to the prevailing market prices at the time of delivery. This approach has proven to be right, particularly in light of what is occurring in other major supply centers. Today, NexGen is the world's most levered Western world company to the future price of uranium and will continue to always be so. Our balance sheet is strong, with CAD 822 million in cash and short-term investments at the end of Q3 2026, as well as an additional CAD 341 million worth of inventory in U3O8, providing significant financial flexibility as we advance Rook I.
NexGen's strategic positioning and unique exposure to the future uranium price upside has provided access to a broad range of attractive and accretive financing alternatives. These include strategic financings, prepayments, project financing. Importantly, our existing liquidity allows us to be highly disciplined in assessing these alternatives and selecting the optimal funding package to preserve flexibility and continue to maximize long-term shareholder value by successfully executing the construction of the Rook I project. Importantly, we continue to achieve key construction milestones to scope, on schedule, on budget, and safely. Construction activity accelerated materially during the third quarter, with earthworks and critical surface infrastructure advancing right across the site. The critical path exhaust shaft pad, civil, and concrete foundational work has commenced. Earthworks for the airstrip expansion to 5,840 feet is complete, providing the capacity to accommodate large jet aircraft by the end of the year.
The construction facilities pad civil foundations are substantially complete, supporting temporary construction facilities and the primary batch plant. The shaft sinking contractor has been mobilized to site, along with the freeze plant, which we strategically procured in 2023. That will be delivered to site in January 2027, with temporary freezing commencing in March of 2027, a key milestone on the critical path. We will go into more detail during the visual slideshow at the conclusion. Detailed engineering continues to progress in alignment with the overall project schedule, with a focus on civil packages, shaft infrastructure, and site-wide utilities. NexGen have also awarded key construction contracts across aggregate crushing, earthworks, concrete, shaft sinking, steel buildings, and power generation. Procurement activities continue to accelerate, with procurement for over 50 process plant long lead items in progress as we speak, along with the procurement for underground equipment.
The progress achieved through Q3 reflects the consequence of significant detailed planning over many years during permitting and our focus on safe execution. Let's walk through the last construction photos through the link included in today's news release. They provide a clear visual update on the significant progress being made across the site, scale, and work now underway as we continue advancing Rook I toward production. Just running through the slides here. This is the eastern end of the extended runway of 5,840 feet, which was completed on October 23, 2026. Permanent access road is on schedule for November 26, and the runway electrical systems are on schedule for February 15, 2027. This slide is two pictures of the exhaust shaft and temporary power facility pads.
All, as we discussed during the call, the civil works are largely completed for both of these activities in preparation for the arrival of the batch plant and the foundations to support the freezing for the freeze plant and the subsequent freezing of the exhaust shaft in Q2 2027. The production shaft pad, they are already complete and ready for civils that are scheduled for completion on December 16 of this year. Slide six is showing construction facility pad. That is including the primary batch plant area, the temporary facilities area as well. As you can see, snow started falling at site as well. Moving to the secondary batch plant, already arrived or being prepared for arrival at site, and first concrete pour is scheduled for December 16, 2026.
This is a picture of the primary batch plant, which will support project construction by producing and supplying concrete for the foundation, structural works, and other critical site infrastructure. It is currently being unloaded in the Port of Houston and then making its way to site. All components are scheduled to arrive at site by December 4, 2026, with installation occurring during the first quarter of 2027. The stockpile facility, clearly all the earthworks have been completed on October 15, 2026. Moving along to the waste pad, or the waste management facility pad, that is temporary storage of the site waste prior to the treatment or disposal. Clearing and grubbing of those activities are complete, with cut and fill operations underway and scheduled for completion on December 18, 2026. This is the installation of the effluent diffuser, which is a 500-meter pipeline that was completed on August 30, 2026.
Highly complex operation involving multiple contractors all working together under the project management of the NexGen team, with successful installation, which required barges, cranes, and divers to deploy. The pad and road finishing activities are underway and are on schedule for completion by December 18, 2026. The exploration core yard expansion and mineralized cutting tents, that core yard is being expanded to accommodate or be prepared, ready for the total 2027 drilling campaign for PCE. That is clearly indicative of our confidence around the PCE resource and how much core is going to be required, or core storage is going to be required as a result of our drilling program at PCE in 2027. Expanded temporary accommodation at the camp expansion. Again, this was completed on June 2026, on time and budget. Accommodation is now on site for 570 people, including an additional 200-person camp as well.
We have capacity for over, well, 770 people with respect to the construction activities at site. Septic tank absorption field as well, on schedule and completion for December. The Clearwater Bridge, this was installed by the Saskatchewan Highways Department, greatly appreciated by NexGen, and reflecting that the government’s commitment to the project in ensuring that appropriate transport infrastructure is in place to support the more heavy haulage vehicles coming to and from site going forward. Thank you, and I will hand over to the operator to open the call for any questions that anyone may have.
Operator
Ladies and gentlemen, we will now begin the question and answer session. To join the question queue, you may press star then one on your telephone keypad. You will hear a tone acknowledging your request. If you are using a speakerphone, please pick up your handset before pressing any keys. Should you wish to decline from the polling process, please press star followed by the number two. We will pause for a moment as callers join the queue and while we prepare the Q&A roster. Our first question comes from George Eadie from UBS. Please go ahead.
George Eadie
Yeah. Hey, Tim. Thanks for the update today. Can I just ask, on the cash spend, the run rate stepped up in Q3 as expected. Could you maybe help us think about that sort of run rate from here for the next couple of quarters? Then just in regards to that, when sort of some of the bigger elixir capital come and thinking about your current liquidity buffer, when you sort of need to, at latest, finalize the sort of next funding strategy? Thank you.
Leigh Curyer
Yeah. Thanks, George. Yeah, look, we are funded through to the end of Q3 2027 as we speak with our cash and short-term investments. We have been spending more, like over the last quarter, and construction is well underway. The bigger drawdown on our cash reserves starts commencing as we start sinking the shafts. They are scheduled for the beginning of Q3 2027. So, yeah, we have got plenty of runway. We have got plenty of options in front of us with respect to financing, and we will be answering that question in a manner that keeps the optimization of project construction intact. We will be reporting on that in due course.
George Eadie
Yeah, great. Thanks, Leigh. Just the strategic inventory, you still do not view that as a source of funds, is that right? Then if I can squeeze one more into that as well, just some of the bigger CapEx spends with the shaft sinking, like, are those Can you remind us of the contracts? Are they fixed yet, or are they in terms of price, or are they still TBD?
Leigh Curyer
Yeah. Firstly, we won't be selling the inventory at all or as a source of financing. With respect to your second question around the shaft sinking contract, we have signed that contract. That contract has come out right in line with our August 2024 financial cost on the Rook I project. That purely validated, because costs have gone up over that time, that we were ultra-conservative in our financial cost calculation with respect to the sinking of the shafts. Shaft sinking, a large component of it is labor, and we are all aware, as widely reported, that there's inflationary pressures and wage pressures. The way we've got the contract set up is that we have complete transparency and management of those costs. If they go up, we will pay them.
The shaft contractor is strongly incentivized around its sinking rates with respect to those shafts, and those sinking rates have had an enormous amount of analysis and validation around them with respect to the rock conditions. As everything we've done at NexGen throughout our 16-year history, we have been conservative and met market expectations in everything we've done, and the construction of this project will be no different. I would also just add-
George Eadie
Okay. Thanks, Leigh.
Leigh Curyer
That we're also. Well, I'll just also add that we have already locked in the purchase of a number of items of equipment where we have identified even, if they are to arrive in year four of the construction period, we've already ordered some significant items to ensure that they arrive on time and at the cost that we expect. As I said, we've been planning the construction of this project for over seven years. We know exactly what we're doing on every day over that four-year construction period, and I basically need to date that back because we're already well into it, and who's doing it, and which contractors are going to support NexGen in doing it.
By virtue of the slides that we went through, you'll see the dates are very specific as to the day as to when things are start and finished, and that is indicative of the level of planning that we've gone to.
Operator
The next question comes from Ralph Profiti from Stifel. Please go ahead.
Ralph Profiti
Thanks, operator. Leigh, just one question from me on the geotechnical side. You actually just touched on it in your previous answer, and this 60-hole program was very successful in identifying sort of rock quality and compressive strength and things like that. Just wondering what follow-up work is being done, and what happens now on the geotechnical side, and what comes next between now and, say, initiation of temporary freezing in March of 2027?
Leigh Curyer
I'll answer the first bit, and if I've left any gaps, I'm sure Travis or Chris will be happy to jump in. But holistically, we have completed a full geotechnical assessment of the shaft conditions themselves. So, we've drilled pilot holes right down the middle of the exhaust and the production shafts. We've drilled geotechnical holes right throughout the ore body, right throughout where the underground tailings management facility is going to be located, and also in a broader sense around the project as well. I dare say, or I will say, I am unaware of another project that's had such geotechnical testing to this extent prior to actual construction. We are very aware of every millimeter that we're drilling through with respect to the exhaust and the production shafts. Now, they are the two most critical items of this entire construction process.
As we highlighted in our webinar on September 1, we've been extremely transparent as to the ground conditions that we expect, the reasons for them, and for those who have been fortunate enough to go to site, have seen the core firsthand, and can attest to the competency of that and the consistency. To answer your question, Ralph, there's no further geotechnical work to be done prior to the commencement of excavating the exhaust shaft, commencing at the start of Q3 2027.
Ralph Profiti
Got you. Thanks so much.
Operator
The next question comes from Mohamed Sidibé from National Bank Financial. Please go ahead.
Mohamed Sidibé
Hi, Leigh. Thanks for taking my question, and good to see the progress at site. Maybe in terms of your procurement packages and contracts, the shaft sinking contract has been signed, but could you remind us of any other procurement packages or contracts that are yet to be awarded that may be kind of driving maybe the biggest cost or schedule risk in your opinion? Thank you.
Leigh Curyer
Well, I'll start. The major ones have been issued. We've got over 50 at the moment that we're currently issuing, and there's a significant number of more. Around the major items of construction, we have the batch plant for the foundations. We have the freeze plant, which we procured back in 2023, over three years ago. It's been located in a shed, ready for transportation up to site for quite a number of years now. The other one would be the power plant, which we don't need until year four, but we've already procured that. We'll put the order in and got the contract terms around it. I would say they would be the major ones as we speak. We haven't encountered any elevation of risk around delivery in accordance with our construction schedule at all.
I think that's a result of the level of detailed planning that we've conducted in the seven years prior to actually being approved to start construction of this project. You can see by virtue of how quickly the runway has gone in, the expansion of that camp to 770 people in an elite environmental manner that we are incredibly busy at site at the moment. There's 376 people. There's an enormous amount of activity on site, and everything is going. It's in this order. I want to be very clear on this. Everything is to scope. We will not compromise the scope, which is in the long-term, highly economic interests of this project, whilst maintaining absolute elite environmental and safety standards, incorporating or optimizing as much community contracting and employment as achievable, where we're currently leading Canada in respect of that.
It's well under management, and the major items we've put a lot of work into, and we're focused on them, and it is going according to our schedule, scope, and cost as we speak. We're constantly reviewing it. It's not like one and done, and everything's finished every day. We're constantly reviewing it, constantly mitigating, and that will continue. I can tell you now, this project will be built to scope and in the most efficient time and cost achievable. As I said, it's a function of the team that we've got at NexGen, that we've assembled over the past seven years, and the granular detail that we've put into the planning and the risk mitigation around it. I just encourage everyone to keep watching our progress.
Go back to the webinar on September 1 to see when things are happening and how that compares to what we're presenting in every quarterly call, and hold us accountable to that. There's no fear there whatsoever. There's huge excitement at site, and it's accelerating as we speak.
Mohamed Sidibé
Thanks a lot for that color, Leigh. Maybe for my second question, if I may, for Travis maybe, just on the contracting front and offtakes, I think just given the recent policy shifts in, not policy, but the midterm election won by the Democrats and questions around data centers and hyperscalers. Just wondering, from a utilities perspective, has anything changed in terms of your conversations and how they're approaching long-term contracting? Or it's the same kind of strength and bullishness that we've seen since the last few years? Thank you.
Travis McPherson
Yeah. Thanks, Mohamed. Short answer is no, we haven't seen any change with respect to that. We wouldn't forecast any, or any material anyways. There's announcements today out of some of the SMR companies and how they're advancing. The midterms are obviously specific to the U.S. That's obviously a very important jurisdiction, one that's supportive really across the aisle of nuclear power and has been for a long time now. We're not just talking to U.S. utilities, we're talking to utilities all over the world. So, there's a ton of interest there for our project, as we said earlier, and our product, and with urgency. So, yeah, no change there as a result of the midterms.
Leigh Curyer
No, I'll just.
Mohamed Sidibé
Thank you.
Leigh Curyer
I'll just add, at the Global Uranium Conference in Adelaide, it was normally a conference where you don't have, or in the past, there haven't been a lot of utilities. Asian utilities were well represented, and they were very open about accessible supply of uranium from 2030 onwards. They've got a real concern over it, and that demand is insatiable. They are well aware that Kazakhstan are building their own strategic inventory to support their own nuclear initiatives. The takeaway was that they've got basically all they're going to be allowed to procure is pretty well done. So, it's materializing. Whilst you're not going to see that directly in the spot price, spot price is rising, long-term price is at a historic high and going further. The three and five year is well into the hundreds and going higher. So, it's happening.
People should look at all of those components when trying to gauge these market fundamentals and how they're playing out. As NexGen and having been in the sector since 2002, but particularly as NexGen's history, this market opportunity is, I think, the most compelling in all commodities, without a doubt. As everyone knows, I bang on about it. I'm very technically and financially fact-driven, and that assessment is based on that, technical and financial fact. It's incredibly exciting for investors in NexGen and also the other uranium cohort.
Mohamed Sidibé
Thanks for that, Leigh Curyer. Thank you.
Leigh Curyer
Thanks, Mohamed.
Operator
Once again, if you have a question, please press star then one. The next question comes from Bill Peterson from JPMorgan. Please go ahead.
Bill Peterson
Yeah. Good morning, and thanks for taking the questions and all the progress updates. You are hiring a lot of people, you are going through training and so forth. How should we think about manpower additions over the next 12 to 18 months? What type of inflation are you seeing with such additions? I guess more broadly, how should we think about expenses, salaries, given the big step up in 2026?
Travis McPherson
Yeah. Look, the training programs have always been, or have been a big focus of ours going back to 2022, because, frankly, before everyone was talking about it being hard to hire people and labor shortages and this and that, we have always found it hard to find people because we are looking for the right people. We have always taken time to train them, identify them, and onboard them the right way. We are not finding any challenges with respect to that. Anytime we put out for applications, we literally get thousands of interested people for each one of those positions. Yeah, we are not seeing any issues there. We are on top of it. We have been for a long time. We are seeing the fruits of those early investments now.
We just, as an example, did a heavy equipment operator training program and had 47 people enter it, 47 people graduate, and 10 immediately got hired at our site, with the rest working with various contractors of ours to fill out their employment. That is just a small example of these training programs ongoing. With respect to wages and that sort of thing, like you said, as Leigh said, we are focused on the scope and the schedule, number 1 and 2. We are willing to pay people to actually do the work and do it really well. That does not take a ton of people when you get the right people. You pay the right people the right amount, and you do not hire five people to do one person's job.
Leigh Curyer
Yeah. We've even actually reduced the level or the overall G&A cost as well over the quarter and going into 2027. At a managerial level, the scale of activities or the spend over the course of Q3 and going into full year 2027, the G&A component is actually going to decrease as a percentage. We have a very highly focus on every dollar we spend. I've got to say, at the moment, in terms of labor rates, the actual cost on a per-hour basis, we haven't experienced a significant increase in cost over the 2026 and 2025. I think that's a combination of a couple of aspects. Very strong management of them, but also people are wanting to come and work at NexGen, given the project that we're working on and the conditions at NexGen and the advancement.
It's another factor that you've got to really manage closely and be ahead of. With the training programs that we've put in place early, we're starting to bear the results and benefits of that planning.
Bill Peterson
Yeah, thanks for those comments. Maybe stepping back and thinking about the bigger CapEx picture. On the investor day, you pointed out that 2027 looks to be the peak CapEx year. First of all, I want to confirm, at least two months on, that's still the case. I guess if you do the math, it looks around CAD 600 million. Is that the right way to think about it as of now, especially taking into account the commentary you just made?
Leigh Curyer
Yeah. That's still completely valid, and we expect it to be during 2027. Yeah.
Bill Peterson
Thanks.
Operator
The next question comes from Graham Tanaka from Tanaka Capital Management. Please go ahead.
Graham Tanaka
Hi, guys. Congratulations on your progress. I am glad things are proceeding on schedule, on budget. Could you confirm or again repeat what you think the all-in cost per pound will be at production? Maybe give us a little hint as to what might happen with that curve as you go from the first to second to third year cost per pound. Also, I had questions on your reserves, and basically mine life plans with scalability upwards and flexibility going forwards. Thank you.
Leigh Curyer
Thank you, Graham. I will start and then hand over to Travis. The cost estimate, the production rate, and all of that as per the definitive feasibility study is maintained in that. With respect to PCE, obviously, there is a lot of interest in it, given the obvious upside to the NexGen story that it will deliver. That is still subject to future resource calculation, engineering studies, environmental studies as well, and obviously subject to permitting. I will just say that the likely development scenario would be, and as I said, qualified with respect to it, would be subject to permitting, et cetera. We would not foresee any material challenges around that, given that we have already received the permit for the Arrow deposit. There is still extensive mineralization that we have intersected through the drill bit that is outside the current grade shells and mine plan of Arrow.
I think a logical development scenario is Arrow, as detailed in the definitive feasibility plan, ongoing production at Arrow as we prove up additional, increase the drill density of those intersections in and around Arrow, and also below the current Arrow grade shell. Also looking at how PCE is optimized once we have an initial resource statement on PCE, which we will be aiming for in around the start of Q3 2027, obviously subject to the timing of receiving assays. So, very exciting. NexGen is clearly much bigger than just Arrow itself, even though Arrow is number one in the world. It's a great position to be in. I think the exploration team is doing a magnificent job with the five rigs on PCE. They will be having a short break over Christmas and then getting right back into it at the start of 2027.
Graham Tanaka
And yes, what the cost per pound, getting back to that, what is that looking like relative to your plans even seven years ago? I am just wondering how much that comes to per pound.
Leigh Curyer
Well, cost per pound as validated in the August 2024 financial cost was just under $10 a pound U.S., with an all-in cost at about $14 U.S.
Graham Tanaka
Okay. Today, what would that estimate be?
Leigh Curyer
Well, it is maintained as per the August 2024 financial cost that we published. It is the same.
Graham Tanaka
Fabulous. Congratulations. Thank you.
Leigh Curyer
Thanks, Graham.
Operator
Again, if you have a question, please press star then one. Our next question comes from Craig Hutchison from TD Cowen. Please go ahead.
Craig Hutchison
All right. Good morning, guys. Just on the financing piece, you guys mentioned that you are financed through Q3 of next year, but just can you talk to what the cadence is around the financing? Do you expect to announce a series of financing measures together, or can we expect maybe some of these announcements to come independently? Just curious on your recent thoughts around prepays as well. Thanks.
Leigh Curyer
Yeah, look, it's dependent on a number of things, market conditions at the time, et cetera. Look, I think as we stand, it will be a combination of those various alternatives, not just one of them. Rising uranium price certainly assists in getting a lower cost of finance, be it whatever form it may be in. So, yeah, I would like to be more specific, but that is as specific as we can get at this point in time. As I said, as we sit here, we would be expecting a combination of one or more of those activities that we're looking at. We are in negotiation for a prepayment with entities both in and outside of the U.S. as we speak. There's a number of prepayment options that we're looking at.
Very importantly, any decision around that is tied to maintaining leverage to the future price of uranium at the time of delivery. So, that is our approach and our guiding principle in those prepayment negotiations.
Craig Hutchison
All right. Thanks, Leigh.
Operator
This concludes the question and answer session. I would like to turn the conference back over to Leigh Curyer for any closing remarks.
Leigh Curyer
Thank you. Thank you, everyone, for attending today and joining our call. We are in construction mode, and we are working on what is the world's highly important newest uranium project. The timing is perfect. We see a market where supply remains structurally constrained while demand for secure, reliable nuclear power continues to accelerate, precisely as Rook I is advancing construction and will be in production in a few short years from now. In closing, the safe and successful execution and community advancement remain at the core of everything we do. We are delivering Rook I to the highest standards, importantly to scope, and within the most efficient time and cost achievable, while we continue to grow the opportunity across our broader district in creating long-term value for our stakeholders. We invite and expect better, and always will be delivering better in everything we do.
With that, it is an exciting time in the industry, incredibly exciting time at NexGen Energy. I would like to take the opportunity for the team that is on the call and the team out at site, they are doing a magnificent job in the delivery of this hugely material project on a world scale. Thank you.
Operator
This brings to a close today's conference call. You may disconnect your lines. Thank you for participating, and have a pleasant day.
Financials CAD · E = consensus estimate · column links open the source filing
Revenue and net income
FY2022
FY2023
FY2024
FY2025
EBITDA
-$57.97M
-$82.93M
-$75.99M
-$87.64M
Net Income
-$60.27M
$70.17M
-$77.56M
-$309.68M
Diluted EPS
-$0.12
$0.16
-$0.14
-$0.53
EPS Growth
-53.8%
-233.3%
-187.5%
+278.6%
Operating Cash Flow
-$20.18M
-$52.62M
-$24.09M
-$47.51M
CapEx
-$354.00K
-$6.07M
-$2.36M
-$505.00K
Free Cash Flow
-$20.53M
-$58.68M
-$26.45M
-$48.02M
Cash
$102.68M
$290.74M
$476.59M
$1.12B
Total Debt
$82.48M
$160.42M
$456.71M
$586.91M
Enterprise Value
$2.87B
$4.74B
$5.38B
$7.80B
FY2022
FY2023
FY2024
FY2025
SG&A
$22.82M
$45.79M
$46.45M
$49.41M
Other Operating Expenses
$35.15M
$37.14M
$29.53M
$38.22M
Operating Income
-$59.78M
-$84.74M
-$78.24M
-$89.84M
Interest Income
-$2.79M
-$6.95M
-$7.93M
-$17.54M
Interest Expense
$2.39M
$6.25M
$32.61M
$46.73M
Non-Operating Income
$3.39M
-$158.49M
$8.72M
$9.01M
Other Non-Operating Income
$3.80M
-$157.79M
-$15.96M
-$20.18M
Pre-Tax Income
-$61.31M
$68.76M
-$82.13M
-$295.57M
Income Tax
-$1.04M
-$1.41M
-$4.57M
$14.11M
Net Income
-$60.27M
$70.17M
-$77.56M
-$309.68M
Net Income to Common
-$56.59M
$80.82M
-$77.56M
-$309.68M
EPS (Basic)
-$0.12
$0.16
-$0.14
-$0.53
EPS (Diluted)
-$0.12
$0.16
-$0.14
-$0.53
Shares Outstanding (Basic)
479.68M
498.24M
554.76M
588.40M
Shares Outstanding (Diluted)
479.68M
529.21M
554.76M
588.40M
Margins
Effective Tax Rate
1.7%
-2.1%
5.6%
-4.8%
Other
Net income attributable to minority interests and other